Tasks with an actual start date but no %age done do not publish

Tasks with an actual start date but no %age done do not publish

Post by VGhhcm1hZ2 » Sun, 21 Sep 2008 08:49:00


We set a task as started by entering an actual start date as today's date,
but do not enter an work done as it has just been started. However when we
publish that task to the server, in web access it does not show the actual
start date.

However if we enter an actual start date and set the %age to even 1% and
publish it. Web access shows the actual start date and 1% done correctly.

Is this by design or a bug? I mean Proj Pro let's you set and actual start
date with any work done. So I would have though web access would show that.
 
 
 

Tasks with an actual start date but no %age done do not publish

Post by UGF1bCBDb2 » Sun, 21 Sep 2008 17:16:01

Without any actuals an assignment has yet to start, so there is no Actual
Start date and it does not make sense to add an actual start date without any
actual work or costs.

This is very much by design.
--