Post by Sm9saWVGYX » Sat, 08 Mar 2008 09:30:00


Hi there, I am totally confused. I have entered in FtoS predessors but the
gant chart does not reflect the entry. It does not move the dates out based
on the predecessor. Is there something I am doing wrong.
 
 
 

finish to start predecessors do not work righ

Post by QlNQ » Sat, 08 Mar 2008 13:15:00

Dear Microsoft Office Project User,

I undersand your question as when F-S dependency is set between tasks, the
Gantt Chart does not reflect the changes in terms of the movement of
successor Gantt Bar to start as soon as the Predcessor completes.

This problem may arise when the start / finish dates of the tasks has been
keyed in directly; this create a "Start Not Earlier Than" constraint for the
tasks (You would see a blue / red calendar icon in the Indicators column of
Gantt Sheet).

By default, Microsoft Office Project supports constraints than relationship
and hence you may see this behaviour by the scheduler.

Solution is to change the constraint types of the tasks to "As soon As
possible", so that the constraints are removed and the relationship is
respected.

You can avoid this problem in future by not entering the Start and/or Finish
dates in the schedule and sequencing the tasks through dependency; Microsoft
Office Project as a result calculates the Start and Finish dates based on the
relationship.

Please let me know if my answer helps.

Regards
Sai, PMP

 
 
 

finish to start predecessors do not work righ

Post by Julie » Sat, 08 Mar 2008 20:24:22

Hello Jolie,

In addition to Sai's suggestions, make sure your calculation is set to
automatic. See Tool > Options, Calculation tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://www.yqcomputer.com/
about Microsoft Project