Post by ks200 » Tue, 09 Mar 2010 23:50:05



Hi
Could someone tell me the difference between the following key words
- Unstarted task
- Task Starting Soon and
- Should have started task
Thanks
KS


--
ks2008
------------------------------------------------------------------------
ks2008's Profile: http://www.yqcomputer.com/
View this thread: http://www.yqcomputer.com/

http://www.yqcomputer.com/
 
 
 

Unstarted task , Task Starting Soon and Should have started task

Post by salgu » Wed, 10 Mar 2010 00:17:19


Unstarted Task - task that hasn't started yet
Task starting soon - task that is scheduled to start soon
Should have started task - task that is scheduled to have started that
hasn't started.

 
 
 

Unstarted task , Task Starting Soon and Should have started task

Post by Trevor Rab » Wed, 10 Mar 2010 01:13:37

In the Unstarted Tasks Report, the Unstarted Tasks filter is used, so the
definition is whatever the filter comes up with, which is just Actual Start
= NA.
In the Tasks Starting Soon Report, the filter used is just the Date Range
Filter, so "soon" means whatever dates the user chooses.
In the Should Have Started Report, the filter is the Should Start By filter,
which is just a user input date, and tasks which have actual start = NA.
--
Trevor Rabey
0407213955
61 8 92727485
PERFECT PROJECT PLANNING
www.perfectproject.com.au